The campaign ended successfully
With support from people in Trebinje, the region and abroad, we secured 210 m² — 6 more than the original target. The new professional surface was purchased, prepared and used at the first “3×3 Trebinje 2026” tournament.
The result in numbers
The campaign exceeded its original target because support continued after the first 204 squares had been filled.
From flooring to first tip-off
We did more than buy the surface. Association members, friends and volunteers prepared and marked it immediately before the first tournament.
Court complete · 2026




The court in play
The new surface was put to use immediately. It hosted the first senior and junior “3×3 Trebinje 2026” tournament.
View tournament photos and reportDonor wall
The first 204 squares represent the people, families and companies who made the professional surface possible. Squares 205–210 remain recorded as support beyond the original target.
Swipe the court left or right to see the remaining squares.
Beyond the original target
Another 6 squares were funded after the goal was reached. The current net result is 210 funded squares — 6 beyond the original 204. Every extra square remains permanently recorded.
The support that built the court
For part of the recorded support, the backend contains structured location data: 179 m² with location data.
Location figures cover 179 m² for which those details are available; the final campaign result remains 210 m². The recorded contribution view was last updated on .

To our community abroad
Your support crossed borders and became part of every future 3x3 game played on this court. Thank you for carrying Trebinje with you.
Transparent to the finish
The final supplier invoice and supporting transport and import documentation provide a more precise procurement breakdown. The euro campaign figure represents 210 recorded support squares at €40 each.
| Item | Amount |
|---|---|
| Supplier / surface — recorded on the supporting document | BAM 12,380.87 |
| Transport — recorded on the supporting document | BAM 750.00 |
| Freight forwarding and customs costs — recorded on the supporting document | BAM 810.00 |
| Difference to the invoiced taxable base | BAM 25.22 |
| Final invoice taxable base | BAM 13,966.09 |
| VAT (17%) | BAM 2,374.24 |
| Total invoiced cost | BAM 16,340.33 |
| Total raised | €8,400 |
| Centrošped invoice item | Amount |
|---|---|
| Forwarding services, commission, guarantee, forms and JCI fee | BAM 210.00 |
| VAT on taxable services | BAM 32.30 |
| Import VAT under the JCI | BAM 2,349.55 |
| Centrošped invoice total | BAM 2,591.85 |
The Centrošped invoice is addressed to HERC Gradnja and documents a supporting procurement cost. Its BAM 2,591.85 is therefore not added a second time to the final BAM 16,340.33 invoice. The document does not show a separate customs-duty line; it lists forwarding services, a JCI fee and import VAT.
The 210 m² figure is the final campaign result and the number of funded support squares. The invoice records 197.82 m² of physical modular flooring delivered under the supplier’s calculation. The two figures therefore use different accounting categories.
A new phase of support
Thank you to everyone who continues supporting the centre and its new projects after the court campaign. Only confirmed donations whose donors selected public display appear here.
Support continues
You choose the amount. PayPal donations remain available to support future tournaments, youth programs and equipment care. Bank transfer details are listed below if you prefer to contribute directly.
PayPal donation
Enter your details, then you will be redirected to PayPal to securely complete the payment.
Enter your details here and PayPal securely completes the EUR payment. Public display is never required.
International bank transfer
Questions? Email 3x3centar@gmail.comor call +387 65 992 587.
The road to the first tip-off
The court surface was purchased and the supplier invoice issued to 3x3 Centar.
Volunteers assembled the court, measured it and painted the playing lines.
The first 3×3 Trebinje tournament on the new surface was completed. Read the tournament report.
Frequently asked questions
Yes. It arrived in Trebinje, was installed and hosted 3×3 Trebinje 2026. The redacted supplier invoice is published above.
The court purchase is complete, but 3x3 Centar’s work continues. Future contributions are not numbered 211 and onward. They support the hoop, lighting, equipment, new events and youth programs.
Yes. Your name may be displayed or hidden. If your country is known, the anonymous donation still counts toward that country’s support.
Donate through PayPal or make an international euro bank transfer.
Senior and youth tournaments, Trebinje Basketball League, charity tournaments and other sporting events.
Yes. Companies can support future events and programs by contacting us directly.
From the heart, thank you
Together we bought it, assembled it, marked it and opened it with a first tournament. Thank you for believing in the idea before its first basket.